Cost of $40M;
cost avoidance $13M
|
|
|
| · |
Completion by
2008; schedule savings of 9 years
|
|
|
| · |
25 land transfer
sub-parcels; 65 PRSs; 5 canyons
|
|
|
|
- |
Risks near people
are addressed first
|
|
|
|
- |
Footprint
of the EM responsibility reduced from nearly 50 mi2 to 38 mi2
|
|
|
|
|
(12 mi2
reduction)
|
|
|
|
- |
EM
responsibility for private and county owned property is completed in
|
|
accordance with
Public Law 105-119
|
|
|
|
- |
EM responsibility
for the land transfer parcels is completed
|
|
|
|
- |
Turnkey,
performance-based subcontract with contractor incentives
|
|