PRS Number PRS Name HSWA      SWMU NFA Proposed Document Title LAUR     No * Virtual Reading Room?
21-001 Container storage No No RFI Work Plan OU 1106 91-0962 Yes
21-002(a) Container storage areas located throughout TA-21 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-002(b) Container storage No Yes RFI RPT TA 21:  PRS 21-002(b) 96-2260 No
RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plans for PRSs 21-002(b), 21-013(c,e), and 31-001 No No
21-003 Container storage - RCRA Unit Yes No RFI Work Plan OU 1106 91-0962 Yes
21-004(a) Aboveground tank No Yes RFI RPT TA 21:  PRSs 21-028(d,e) ACS Area, 21-004(a-c) Above Ground Tanks 96-2041 No
RFI Work Plan OU 1106 91-0962 Yes
21-004(b) Tank and/or assoc. equipment Yes Yes RFI RPT TA 21:  PRSs 21-028(d,e) ACS Area, 21-004(a-c) Above Ground Tanks 96-2041 No
RFI Work Plan OU 1106 91-0962 Yes
21-004(c) Tank and/or assoc. equipment Yes Yes RFI RPT TA 21:  PRSs 21-028(d,e) ACS Area, 21-004(a-c) Above Ground Tanks 96-2041 No
RFI Work Plan OU 1106 91-0962 Yes
21-004(d) Drain line No Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-005 Disposal pit Yes Yes RFI Work Plan OU 1106 91-0962 Yes
RFI Report for Potential Release Site 21-005 99-4655 No
21-006(a) Disposal pit Bldg 21-2 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-006(b) Disposal pit Yes No Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-006(c) Disposal pit Bldg 21-3 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-006(d) Disposal pit Bldg 21-3 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-006(e) Surface disposal site Bldg 21-4 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-006(f) Disposal pit Bldg 21-4 No No RFI Work Plan OU 1106 91-0962 Yes
21-007 Incinerators Yes Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-008 Incinerator No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-009 Waste treatment lab No No RFI Work Plan OU 1106 91-0962 Yes
21-010(a) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-010(b) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-010(c) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-010(d) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-010(e) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-010(f) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-010(g) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-010(h) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(a) Waste treatment facility Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(b) Sump Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(c) Tank and Sump Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(d) Aboveground tank Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(e) Aboveground tank Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(f) Aboveground tank Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(g) Aboveground tank Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(h) Aboveground tank No No RFI Work Plan OU 1106 91-0962 Yes
21-011(i) Aboveground tank Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(j) Aboveground tank Yes No RFI Work Plan OU 1106 91-0962 Yes
21-011(k) Outfall Yes No Interim Action Plan for TA 21:  PRS 21-011(k) 96-1609 No
Interim Action Report TA 21:  PRS 21-011(k)  HSWA No No
Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-012(a) Dry well Yes - Removed Yes RFI Work Plan OU 1106 91-0962 Yes
21-012(b) Dry well Yes No RFI Work Plan OU 1106 91-0962 Yes
21-013(a) Surface disposal site Yes Yes RFI RPT TA 21:  21-013(a), 21-026(a,b,c) 97-589 No
RFI Work Plan OU 1106 91-0962 Yes
21-013(b) Surface disposal site Yes No RFI Work Plan OU 1106 91-0962 Yes
Interm Measures Plan for Consolidated PRS 21-018(a)-99 No No
21-013(c) Surface disposal site Yes Yes RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plans for PRSs 21-002(b), 21-013(c,e), and 31-001 No No
Final Voluntary Corrective Action Report HSWA: 21-013(c-e), 31-001 96-259 No
21-013(d) Surface disposal site (Cold Dump) Yes Yes RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan For PRS 21-013(d) (addendum) No No
Final Voluntary Corrective Action Report HSWA: 21-013(c-e), 31-001 96-259 No
21-013(e) Surface disposal site Yes Yes RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plans for PRSs 21-002(b), 21-013(c,e), and 31-001 No No
Final Voluntary Corrective Action Report HSWA: 21-013(c-e), 31-001 96-259 No
21-013(f) Surface disposal site No No RFI Work Plan OU 1106 91-0962 Yes
21-013(g) Surface disposal site No No RFI Work Plan OU 1106 91-0962 Yes
Interm Measures Plan for Consolidated PRS 21-018(a)-99 No No
21-014 Material disposal area (MDA A) Yes No RFI Work Plan OU 1106 91-0962 Yes
21-015 Material disposal area (MDA B) Yes No RFI Work Plan OU 1106 91-0962 Yes
21-016(a) Material disposal area (MDA T) Yes No RFI Work Plan OU 1106 91-0962 Yes
21-016(b) Material disposal area (MDA T) Yes No RFI Work Plan OU 1106 91-0962 Yes
21-016(c) Material disposal area (MDA T) Yes No RFI Work Plan OU 1106 91-0962 Yes
21-017(a) Material disposal area (MDA U) Yes No RFI Work Plan OU 1106 91-0962 Yes
21-017(b) Material disposal area (MDA U) Yes No RFI Work Plan OU 1106 91-0962 Yes
21-017(c) Material disposal area (MDA U) Yes No RFI Work Plan OU 1106 91-0962 Yes
21-018(a) Material disposal area (MDA V) Yes No RFI RPT TA 21:  PRS 21-018(a) MDA V 96-2735 No
RFI Work Plan OU 1106 91-0962 Yes
Interm Measures Plan for Consolidated PRS 21-018(a)-99 No No
21-018(b) Material disposal area (MDA V) Laundry Facility Yes No RFI Work Plan OU 1106 91-0962 Yes
Interm Measures Plan for Consolidated PRS 21-018(a)-99 No No
21-019(a) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(b) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(c) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(d) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(e) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(f) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(g) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(h) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(i) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(j) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(k) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-019(l) Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes

21-019(m)

Filter houses/ exhaust stacks No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-020(a) Filter house No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-020(b) Filter house No Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-021 Systematic release (site -wide) Yes Yes Phase RPT 1B for  OU 1106TA 21 93-4390 No
RFI Work Plan OU 1106 91-0962 Yes
21-022(a) Waste lines Yes No RFI Work Plan OU 1106 91-0962 Yes
21-022(b) Waste lines Bldg 21-2 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-022(c) Waste lines  Bldg 21-3 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-022(d) Waste lines Bldg 21-4 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-022(e) Waste lines Bldg 21-5 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-022(f) Waste lines Yes No RFI Work Plan OU 1106 91-0962 Yes
21-022(g) Waste lines Bldg 21-150 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-022(h) Waste lines Yes No Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-022(i) Tank and/or assoc. equipment Yes No RFI Work Plan OU 1106 91-0962 Yes
21-022(j) Tank and/or assoc. equipment Yes Yes RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan For PRSs 21-022(j), C-21-027 No No
Final Voluntary Corrective Action Report Non-HSWA: 21-022(j) 96-248 No
21-023(a) Septic system Bldg 21-3 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-023(b) Septic system Bldg 21-3 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-023(c) Septic system Yes No Interim Action Plan for TA 21:  PRS 21-023(c) 96-2836 No
Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-023(d) Septic system Bldg 21-3 Yes No RFI Work Plan OU 1106 91-0962 Yes
21-024(a) Septic system Yes No Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(b) Septic system Yes No Interim Action Plan for TA 21:  PRS  21-024(b) 96-2837 No
Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan For PRSs 21-024(b,d,h) No No
21-024(c) Septic system  - PCB only site Yes No Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(d) Septic systemVCA for rad Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan For PRSs 21-024(b,d,h) No No
Final Voluntary Corrective Action Report HSWA: 21-024(d) 96-258 No
21-024(e) Septic system Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan For PRS 21-024(e) No No
Final Voluntary Corrective Action Report HSWA: 21-024(e) 96-257 No
21-024(f) Septic system Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan for Potential Release Sites 21-024(f) and C-21-015 99-3407 No
21-024(g) Septic system Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(h) Septic system Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan For PRSs 21-024(b,d,h) No No
Final Voluntary Corrective Action Report HSWA: 21-024(h) 96-256 No
21-024(i) Septic system Yes No Interim Action Plan TA 21:  PRS 21-024(i) 98-1896 No
Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(j) Septic system Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(k) Septic system Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(l) Ind. or san. waste water treat. Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(m) Drain line Yes - Removed Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(n) Drain line Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-024(o) Drain line Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-025(a) Operational facility No Yes RFI Work Plan OU 1106 91-0962 Yes
21-025(b) Operational facility No Yes RFI Work Plan OU 1106 91-0962 Yes
21-026(a) Ind. or san. waste water treat. Yes Yes RFI RPT TA 21:  21-013(a), 21-026(a,b,c) 97-589 No
RFI Work Plan OU 1106 91-0962 Yes
21-026(b) Surface disposal site (sand filter/sludge drying beds) Yes Yes RFI RPT TA 21:  21-013(a), 21-026(a,b,c) 97-589 No
RFI Work Plan OU 1106 91-0962 Yes
21-026(c) Waste water treatment facility (dosing siphon chamber) No Yes RFI RPT TA 21:  21-013(a), 21-026(a,b,c) 97-589 No
RFI Work Plan OU 1106 91-0962 Yes
21-026(d) Outfall No Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-027(a) Ind. or san. waste water treat. Yes No Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-027(b) Outfalls Yes - Removed Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-027(c) Ind. or san. waste water treat. Yes No Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
21-027(d) Drain line Yes Yes Final Draft for the OU 1106 Addendum to Phase RPT 1B, 1C TA 21 94-4360 No
RFI Work Plan OU 1106 91-0962 Yes
Modification to the Voluntary Corrective Measure Plan for Consolidated Potential Release Site 21-027(d)-99 No No
Submittal of Voluntary Corrective Measure Plan for Consolidated PRS 21-027(d)-99(NTISV Project) 99-1613 No
21-028(a) Container storage No No RFI Work Plan OU 1106 91-0962 Yes
21-028(b) Container storage No Yes RFI Work Plan OU 1106 91-0962 Yes
21-028(c) Container storage Bldg 21-3 No No RFI Work Plan OU 1106 91-0962 Yes
21-028(d) Container storage No Yes RFI RPT TA 21:  PRSs 21-028(d,e) ACS Area, 21-004(a-c) Above Ground Tanks 96-2041 No
RFI Work Plan OU 1106 91-0962 Yes
21-028(e) Container storage No Yes RFI RPT TA 21:  PRSs 21-028(d,e) ACS Area, 21-004(a-c) Above Ground Tanks 96-2041 No
RFI Work Plan OU 1106 91-0962 Yes
21-029 Soil contamination area Yes Yes Response to denial of RFI RPT TA 21:  PRS  21-029 No No
RFI Work Plan, Volume II, DP Tank Farm (PRS 21-029)  [Compliance Order 98-01:  Response to Ordered Action] 98-4169 No
RFI RPT TA 21:  PRS  21-029 95-3693 No
RFI Work Plan OU 1106 91-0962 Yes
Voluntary  Corrective Action Plan TA 21:  PRS 21-029 96-1263 No
Final VCA Completion Report TA 21:  PRS 21-029, DP Tank Farm ActivitiesNotice of Violation to Compliance Order at PRS 21-029; RFI Work Plan  to be submitted in 90 days or  a hearing must be  requested within 30 days 96-2408 No
C-21-001 One-time spill Bldg 21-5 No No RFI Work Plan OU 1106 91-0962 Yes
C-21-002 Non-intentional release area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-003 Non-intentional release area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-004 Non-intentional release area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-005 One-time spill No No RFI Work Plan OU 1106 91-0962 Yes
C-21-006 Non-intentional release area Bldg 21-2 No No RFI Work Plan OU 1106 91-0962 Yes
C-21-007 Non-intentional release area No No RFI Work Plan OU 1106 91-0962 Yes
C-21-008 One-time spill No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-009 One-time spill No No RFI Work Plan OU 1106 91-0962 Yes
C-21-010 Systematic leak No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-011 One-time spill No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-012 One-time spill No No RFI Work Plan OU 1106 91-0962 Yes
C-21-013 Disposal pit No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-014 Warehouse No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-015 Building No Yes RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan for Potential Release Sites 21-024(f) and C-21-015 99-3407 No
C-21-016 Storage area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-017 Storage area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-018 Storage area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-019 Storage area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-020 Storage area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-021 Storage area No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-022 Laboratory No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-023 Laboratory No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-024 Warehouse No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-025 Building No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-026 Building No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-027 Machinery No Yes RFI Work Plan OU 1106 91-0962 Yes
Voluntary Corrective Action Plan For PRSs 21-022(j), C-21-027 No No
Final Voluntary Corrective Action Report Non-HSWA: C-21-027 96-247 No
C-21-028 Tank No Yes RFI Work Plan OU 1106 91-0962 Yes
Modification to the Voluntary Corrective Measure Plan for Consolidated Potential Release Site 21-027(d)-99 No No
Submittal of Voluntary Corrective Measure Plan for Consolidated PRS 21-027(d)-99(NTISV Project) 99-1613 No
C-21-029 Aboveground tank No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-030 Aboveground tank No Yes RFI Work Plan OU 1106 91-0962 Yes
C-21-031 Tank No No RFI Work Plan OU 1106 91-0962 Yes
C-21-032 Machinery and tanks No No RFI Work Plan OU 1106 91-0962 Yes
C-21-033 One-time spill No No RFI Work Plan OU 1106 91-0962 Yes
C-21-034 Tank No No RFI Work Plan OU 1106 91-0962 Yes
C-21-035 Aboveground tank No No RFI Work Plan OU 1106 91-0962 Yes
C-21-036 Aboveground tank No No RFI Work Plan OU 1106 91-0962 Yes
C-21-037 Aboveground tank No No RFI Work Plan OU 1106 91-0962 Yes