For immediate release: October 19, 2026
Plutonium warhead core factory in South Carolina receives final go-ahead with new cost, schedule estimates $23.5 billion cost is slightly lower than previous "placeholder" of up to $25 billion; the new December 2038 completion date is three years later The rushed Los Alamos factory meanwhile continues construction and concurrent early operation in attempt to keep new ICBM warheads on schedule Contact: Greg Mello: 505-577-8563 cell Please also see this press release sent to regional media this morning for some local details
Albuquerque and Santa Fe, NM -- This past Friday (October 16), the National Nuclear Security Administration (NNSA) announced that its plutonium warhead core ("pit") factory, under construction at the Savannah River Site (SRS) in South Carolina, had cleared a major milestone ("Critical Decisions Two and Three," CD-2/3), allowing for construction on all its subprojects, not just some. The project, called the Savannah River Plutonium Processing Facility (SRPPF), is now projected to cost a total of $23.5 billion (B), $1.5 B less than the previous crude "placeholder" high-end estimate of $25 B (p. 129) -- this according to reliable Study Group sources.
SRPPF construction is now to be complete ("Critical Decision Four," CD-4) by December 2038, three and a quarter years after the previous estimate of September 2035 (p. 125), again according to reliable Study Group sources.
Pit production cannot commence immediately after construction is completed. Optimistically, an additional three-year startup period is needed (p. 3). Prior studies estimated a 5-year startup but NNSA has been closely studying and practicing how to decrease startup time at its new nuclear facilities.
Study Group director Greg Mello: